Answer

The materials price variance can be calculated at the point of purchase (on quantity purchased) or at the point of use (on quantity used). Calculating at purchase isolates the variance earlier and values inventory at standard, aiding prompt buying feedback; at use, it aligns with the usage variance. The choice affects when the variance is recognized.
Real-world example Calculating the price variance at purchase gives buyers immediate feedback and values stock at standard.

Common follow-ups: What are the two calculation points? | What is the benefit of pricing at purchase?